Answer: Foundation coordination requires confirmed foundation geometry, elevations, anchor locations, design reactions, tolerances, waterproofing interfaces and installation sequence. The local foundation engineer should verify soil capacity and design the supporting concrete or other foundation system. Confirm responsibility for anchors, templates and site inspection in the supply contract.
Setting Out the Connection
The base detail is decided in the drawing set, not on site.
- Anchor bolt diameter, embedment, spacing and projection from the drawing
- Base track fixing method: cast-in bolts, chemical anchors or screw anchors
- Slab edge, plinth and damp-proof course detail under the track
- Position of hold-downs at braced wall ends and corners
Transferring Uplift and Shear
Overturning tension is the load that foundations most often miss.
- Hold-down brackets sized for the calculated uplift at each braced wall
- Continuous load path from roof diaphragm to anchor
- Shear transfer through base track fixings and slab friction only where allowed
- Reinforcement detailed to anchor the tension into the concrete
Tolerances and Site Inspection
Small setting-out errors become expensive once the frame is fabricated.
- Bolt position tolerance agreed and checked before pour
- Level and flatness of the bearing surface verified
- Inspection record and photo set signed before erection begins
- Procedure for a misplaced bolt, agreed in advance
Frequently Asked Questions
Can chemical anchors replace cast-in bolts?
Sometimes, where the design allows and the concrete is sound. Cast-in bolts are preferred where uplift is high, because they are more reliable.
Who designs the foundation?
Typically a local engineer using the reactions and bolt layout supplied by the frame designer, because soil and code are local.
What tolerance is realistic for anchor bolts?
The frame can absorb a small positional tolerance if the base plate holes allow it. The value must be stated on the drawing and checked on site.